Timeline
-
Concept design endorsed by Council
3 May 2021Complete
-
Schematic Design endorsed by Council
2 May 2022Complete
-
Detail design and documentation
May 2022 - July 2023Complete
-
Tender for construction
August - December 2023Complete
-
Contract awarded to Badge Constructions
25 January 2024Complete
-
Construction works
February 2024 - Early 2026In progress
-
New Centre open to the public
Early 2026 (date to be confirmed)Scheduled
Latest News
To date, the following works have been completed:
> the 50m outdoor pool, and
> the Pool Hall building with the indoor 25m and learn to swim pools are almost finished.
To date, the following works have been completed:
> demolition of the former buildings, pools and associated infrastructure
> upgrades to the sewer main and water connections
> earthworks and soil contamination management
> concrete pours for the Learn to Swim and 25 metre pools
> installation of precast walls along the OG Road frontage
Next stages include construction of the pool hall building, concrete pours for the 50metre outdoor pool and installation of a new electrical transformer.