Timeline
-
Syd Jones Reserve Upgrade Concept Plan endorsed by Council
March 2019Complete
-
Syd Jones Reserve Detail Design and construction Documentation developed
March - September 2019Complete
-
Tender for the construction released
October - November 2019Complete
-
LCS appointed as the contractor to construct the Syd Jones Reserve Upgrade
December 2019Complete
-
The majority of works completed
July 2020Complete
-
Syd Jones Reserve Upgrade completed
1 September 2020Complete
-
Open to the public
Friday 11 September 2020Complete